Process features and Introduction
Raw materials receiving and cleaning section:In this section, pellet feeding cleaning and powder feeding cleaning are separated independently and separate dust removal. Dust removal effect is good.
Cleaning equipment:granules sifter SCY80,capacity 20-30T/H;Powder sifter SQLZ60X50X100, capacity 10-15T/H.
First coarse grinding section: This section adopts one hammer mill, and with two pre-grinding bins which can change the grinded materials alternately. Before entering the bins, the impurities are removed by magnetic separation device to ensure the safe operation of the hammer mill.
Grinding equipment : Hammer mill SFSP668×800, 110kw, designed to produce 10-14t/h(¢2.0mm screen hole)
First batching and mixing section: This section adopts 18batching bins, two set of batching system work at same time. It is controlled by the batching program independently developed by our company to realize accurate fast and slow feeding, fast batching and high precision.
Weighing equipment: Dosing scale PCS15/PCS05, dosing precision: dynamic ≤3‰, static ≤1‰.
Mixing equipment: mixer SHSJ3, (22KW, 1500kg/ batch), designed to produce 15-18t/h. Mixture uniformity CV ≤5%.
Pulverizing section: Due to the extruder high requirement for the fineness of raw material, generally 60-120 mesh, this section adopts two pulverizer, each equipped with two pre-grinding bins. They can take turns to store and discharge the material, which reduces the pulverizer's idle time. It adopts the wind type discharging, and be allocated with cyclone, pulse filter, the grinding fineness can be adjusted.
Pulverizer equipment(2sets): SWFL130, 160+15+ 2.2kw;Design time: 3-6t/h per set.
Second mixing section: This section adopts four secondary mixing bins(all round bins), equipped with one batching scale sharing one same computer with first batching system which is convenient for control by one operator.
Weighing equipment: batching scale PCS15, dosing precision: dynamic ≤3‰, static ≤1‰.
Mixing equipment: mixer SHSJ3, 22kw, 1500kg/P, designed to produce 10-15t/h. Mixture uniformity CV≤5%.
Extruding section: This section adopts two set of double screw extruder, equipped with a pre-extruding bin above the each extruder. The extruding bin is designed as a round bin, and equipped with a disk-type feeder to prevent material from forming and discharge smoothly.
Extruding equipment(2sets): SPHS130×2, 185+4+4+15+1.5kw, design output: 3-6T /H per set (discharging hole diameter 4.0mm), drying equipment(2sets): SHGW240×2-7, 0.75+1.1*2+7.5×10+ 0.75kw, design output: 4-6T/H
Coating & Bagging section: This section adopts two set of drum oil coating equipment, equipped with pneumatic gravity diverter before entering the equipment. You can choose whether to spray oil for finished pellets according to different formula requirements. The post-coating section solves the problem that the early phase of the material oil content should not be too much and then cannot meet the oil content requirements. By coating, the feed appearance is good, palatability is better, nutrition is higher. The materials after oil injection are screened and packed after cooling by swing cooler.
Drum coater(2sets): SYPG1000, 2.2kw, design output: 4-6T/H per set,
Swing cooler(2sets): SKLB6,1.1+1.5KW,volume 6m3, design output: 6-8T/H per set,
Packing equipment (2sets): Quick single-hopper granule scale for extruding material, packing range: 20-25kg/bag, 4-6 bags/minute.
Auxiliary section: The dust removal system: it is used in the bagging system which can improve the working environment for workers; Oil adding system and Water adding system: it can improve the feed palatability.
According to the needs of different customers, the scheme can be optimized:
1. This design adopts the single-point dust removal mode, that is, each rotary distributor (powder material) and pellet cleaner is equipped with a pulse filter, which has a good dust removal effect. Single point of dust removal is our company’s humanized design, which can provide a better working environment, but the cost increases. Customers can consider whether to use this configuration according to the actual needs;
2. The quantity of bins can also be adjusted according to the formula of customers, the characteristics of raw materials and other factors, so as to achieve the highest utilization rate and effectively control the production cost;
3. Assembly or welding can also be adopted for the installation of the bin. The assembly bin has a high cost, quick and convenient on-site installation, and the welding silo has a low cost. On-site welding by workers is with high labor intensity and long time. Users can make reasonable choices according to their own needs;
4. In this project, the secondary mixing adopts the process of automatic batching with high automation, if customer need to control the invest cost, we can also used non-automatic batching and mixing process by batch, it can also produce normally only with a lower batching efficiency.
5. The coating equipment we adopt in this project is drum type coater, the oil addition is suggested to not larger than 8%, and it can only coating on the pellet surface, if the customer requires high quality with more oil addition, we can choose vacuum spraying machine which is better for the absorption of oil in the particle core.